Project Date:

 January 2023

Location:

Papua, Indonesia

Project Duration:

1 month including data acquisition and for data processing

Deliverables:

Tie-ins Survey Report

Drawing Tie-ins

 

The Tangguh LNG field is a rich natural gas deposit, discovered in 1994 in the bay of the state of West Papua, about 3,000 km from Jakarta. The reserves were calculated to be around one million tons of liquid natural gas per year, for 20 years.

Tangguh LNG Expansion Project Train 3 consists of the onshore construction of a plant with a 3.8 MTPA (millions of tons per year) liquefaction capacity, onshore receiving facility, LNG and condensate loading berth, boil-off gas recovery, utilities, flares, and associated infrastructure

The new plant had to be integrated into an existing facility with two LNG trains in operation, managing the design accordingly as well as the necessary tie-ins.

BP Berau Ltd. has identified the need for using the 3D laser scanning technology for all tie-ins location, and produce accurate 3D model and also 2D AutoCAD format.