Project Date:

 May 2023

Location:

East Sepinggan Block, Kutei Basin

Project Duration:

4 weeks including quarantine, data acquisition and for data processing

Deliverables:

Site Survey Report

Truview 3D Point cloud

HD Photo and 360 degree panoramic

3D PDMS Semi intelligence model

 

Eni East Sepinggan instruct PT Saipem Indonesia to design, procure, construct and install by-pass line which allow the production of Jangkrik Main directly routed to inlet LTS Train 1. This modification to be done on-board

FPU Jangkrik which currently in operation. This activity to be considered as brownfield modification of existing FPU Jangkrik facility.

The accuracy of the by-pass spool design shall be considered as zero tolerance due to criticality of the installation schedule, safety aspect, logistic and etc. Therefore as essential preparation to intially start design activity, an accurate as-built condition (for the area which impacted by the modification) shall be established as design reference.

3D Laser Scan by PT Tri Panji Puring on the existing facility are planned on the area which impacted by the modification. The result of 3D laser scan will be converted as model reference of PDMS which allow PT Saipem Indonesia to properly and accurately design the by-pass spool.